You think the I-85 bridge was rebuilt quickly?

Over the weekend, Georgia DOT crews worked to replace a bridge over I-24 in Dade County that was scheduled to take just two days.

The bridge was constructed beside the roadway, using a technique called accelerated bridge construction, then moved into place.

The new bridge includes two 12-foot travel lanes and two 8-foot shoulders.

Dade County is located at the Georgia-Tennessee state line.